- Section 1 (Commercial area, Southwest corner of STH 50 & STH 31)
Roadways within this section will be pulverized and resurfaced, along with utility structure adjustments and repairs. Additional work includes curb and gutter repairs. The existing “tee” intersection at the west end of 76th Street will be reconfigured into a new “L”-shaped curb radius configuration to improve roadway alignment and operations.
- Section 2 (Springbrook Meadows Subdivision)
Roadways within this subdivision will undergo a mill and overlay resurfacing process. Additional work includes selective curb and gutter repairs, along with utility structure adjustments and repairs as needed throughout the project area.
- Section 3 (121st Street)
This section has been removed from the 2026 Paving Program by direction of the Village Board.
- Section 4 (St. Johns Lift Station)
This work area is located on the property of St. John’s Monastery, and impacts will be limited to monastery operations only. Improvements include removal and replacement of the existing pavement, replacement of failed stone base areas, and utility structure adjustments as needed.
- Section 5 (Village Green Park Path)
This project consists of construction of a new multi-use asphalt path connecting Village Green Park to the existing sidewalk network within The Cottages development/subdivision. Major work items include grading, stone base installation, asphalt paving, and construction of ADA-compliant sidewalk ramps and connections.
Throughout the project areas, the contractor will perform pavement resurfacing, curb and gutter repairs, utility structure adjustments, and other roadway improvements identified during the design process. These improvements help preserve the condition and longevity of the roadway network by addressing deteriorated pavement, repairing damaged concrete infrastructure, and ensuring utility structures are properly adjusted to match the finished roadway surface.
Generally, all work is located within the public roadway right of way. If it is necessary to work on private property, the village will first obtain approval from the property owner.
Additional information on the pulverize and resurfacing process and some common questions and concerns can be found here.
Schedule: All Work is planned to be constructed by the end of fall 2026. The Village and its contractor are committed to minimizing disruptions and shortening the overall construction timeline. However, please note that weather conditions, utility coordination, and scheduling factors may affect progress. Anticipated completions dates for each section are noted below:
Section 1: June 2026
Section 2: July 2026
Section 3: Removed.
Section 4: TBD
Section 5: TBD
2025 Paving Program
Contractor: Payne and Dolan
The contractor and its subcontractors are currently completing final project items throughout the various 2025 Paving Program sections. Work at this stage primarily consists of restoration activities, including lawn restoration, landscape repairs, and other punch list items. Crews may be working in multiple project areas and not necessarily in a sequential order.
Contact: Tim Kuligoski, Village Construction Supervisor
Phone: (262) 948-8948
Email: [email protected]
116th Street Water Main Extension 
Contractor: Globe Contractors, Inc.
Information: The Village is investing in critical improvements to expand and strengthen its public water system. This project involves installing new water main infrastructure to improve system reliability and extend service to areas that previously did not have access to municipal water. These upgrades will enhance water quality, ensure better fire protection, and support long-term growth within the community. Construction will be coordinated to minimize disruptions to residents and ensure a smooth transition for new connections. During construction, the roadway in the project area will be closed to thru traffic. Local access will be maintained for residents and emergency vehicles.
Project area map:

Schedule: Completion date (Restoration): Spring 2026
Contact: Tim Kuligoski, Village Construction Supervisor
Phone: (262) 948-8948
Email: [email protected]
122nd Street Water Main Extension
Contractor: Globe Contractors, Inc.
Information: The Village is investing in important improvements to expand and strengthen the public water system along 122nd Street. This project includes installing new water main infrastructure to improve system reliability, increase capacity, enhance fire protection, and provide municipal water service to areas that previously did not have access. Most of the water main will be installed by directional drilling within the south ditch of 122nd Street, with the exception of two crossings: the Des Plaines River, where the alignment will shift south beyond the bridge, and the Canadian Pacific Railroad, which will be installed using the jack and bore method. To complete this work safely, 122nd Street will be closed to thru traffic during construction. However, local access for residents and emergency vehicles will be maintained, and construction activities will be coordinated to minimize disruptions as much as possible.
Project Area Map:

Schedule: The Contractor currently anticipates completing the project by May 22nd, 2026.
Contact: Tim Kuligoski, Village Construction Supervisor
Phone: (262) 948-8948
Email: [email protected]