Update on behalf of Kenosha County: Kenosha County's County H and Bain Station Road Roundabout Reconstruction Project is well underway. Please see below for the latest project updates.

Crews have completed the following project work:
Storm sewer installation - COMPLETED
Curb and gutter work - COMPLETED

3-Week Look Ahead:
Final removal of old utility poles
Contour grading
Street lighting electrical work
Concrete truck apron installation
Bike path installation

All project work and closures are weather dependent and subject to change. To learn more about the project or to sign-up to receive project updates, please contact Public Involvement Leader: Cynthia De Vor at (262) 510.8901 or [email protected]